2023 Projects
Atlas Copco USA Holdings Inc. & Subsidiaries (Edwards) (Final Resolution Approved)
Edwards is planning on building a dry pump manufacturing facility and two-story office building at STAMP for Phase I of their semiconductor supply chain factory of the future. The Phase I capital investment will be $209.25 million and plans to create 343 FTE’s.
Project Application
Initial Resolution - Approved January 12, 2023
Public Hearing - January 31, 2023 - Notice - Minutes - Video
Final Resolution - February 2, 2023
Agent Agreement
Project Close Date
Report to PARIS
Horizon Acres Associates, Inc. (Final Resolution Approved)
Horizon Acres Associates, Inc. is seeking to develop six flex commercial/industrial facilities that will total 1,500,000 square feet in the Town of Pembroke on 115 buildable acres. The $142 million total project will be completed in phases, and projects to create 400 FTE’s at full build-out.
Project Application
Initial Resolution - Approved January 12, 2023
Public Hearing - January 30, 2023 - Notice - Minutes - Video
Final Resolution - Approved March 2, 2023
Agent Agreement
Project Close Date
Report to PARIS
GSPP Route 262, LLC (Public Hearing Held)
GSPP Route 262, LLC is proposing to construct a community solar farm project on Townline Road in the Town of Byron. The project will generate 5 MW of AC power.
Project Application
Initial Resolution - Approved March 30, 2023
Public Hearing - April 19, 2023 - Notice - Minutes - Video
Final Resolution
Agent Agreement
Project Close Date
Report to PARIS
LNK Holdings, Inc. (Public Hearing Held)
LNK Holdings Inc. (Craft Cannery) is proposing to acquire and expand an agribusiness facility in Bergen which produces sauces, dressings, marinades and other foods. The project will add 4,000 sq. ft. to the facility and support 4 full-time equivalent jobs and 6 retained jobs.
Project Application
Initial Resolution - Approved May 4, 2023
Public Hearing - May 23, 2023 - Notice - Minutes - Video
Final Resolution
Agent Agreement
Project Close Date
Report to PARIS
2022 Projects
Appletree Acres LLC
Apple Tree Acres, LLC is building a 50,000 sq. ft. stand-alone facility on its property at Apple Tree Acres, in town of Bergen. The project is investing $3.15 million and is pledging to create 3 FTEs.
Project Application
Initial Resolution - Approved January 13, 2022
Public Hearing - February 2, 2022 - Notice - Minutes - Video
Final Resolution - Approved May 5, 2022
Agent Agreement
Project Close Date - June 29, 2022
Report to PARIS: Yes (Project 1801 22 01A)
Franklin Real Estate & Development (Final Resolution Approved)
Franklin Real Estate & Development is planning on building two 7,725 square-foot, 8-unit market rate apartment buildings in the town of Pembroke. Each 2-story building consists of 7 two-bedroom units and 1 one-bedroom unit. The $1.74 million project's buildings will total 15,460 square feet combined.
Project Application
Initial Resolution - Approved January 13, 2022
Public Hearing - February 1, 2022 - Notice - Minutes - Video
Final Resolution - Approved February 3, 2022
Agent Agreement
Project Close Date
Report to PARIS
J&R Fancher Property Holdings (Final Resolution Approved)
J&R Fancher Property Holdings LLC is planning on building a facility at Buffalo East Technology Park in the town of Pembroke on 3 acres.
The facility will total 52,332 sq. ft. of which 45,000 sq.ft. pre-engineered steel warehouse building with 7,332 sq. ft. office. The project is investing $3.25 million and planning on creating 4 FTE’s.
Project Application
Initial Resolution - Approved March 3, 2022
Public Hearing - March 21, 2022 - Notice - Minutes - Video
Final Resolution - Approved March 29, 2022
Agent Agreement
Project Close Date
Report to PARIS
La Fermière Inc. (Public Hearing Held)
La Fermière Inc. is planning on building a 50,000 sq. ft. facility to produce French yogurt at the Genesee Valley Agri-Business Park in the town of Batavia on 20 acres.
The project is planning on investing $25 million and planning to create 68 FTEs in the first 3 years of operation (and plans to create a total of 135 FTEs by year 5).
Project Application
Initial Resolution - Approved May 5, 2022
Public Hearing - May 23, 2022 - Notice - Minutes - Video
Final Resolution
Agent Agreement
Project Close Date
Report to PARIS
O-AT-KA Milk Products, LLC
O-AT-KA Milk Products, LLC is planning on building a 3,200 sq. ft. addition to its existing facility in the town of Batavia to support increasing capacities for cream based liquor beverage production.
The project is planning on investing $3.1 million and is planning to create 2 FTEs.
Project Application
Initial Resolution - Approved May 5, 2022
Public Hearing - May 23, 2022 - Notice - Minutes - Video
Final Resolution - Approved June 2, 2022
Agent Agreement
Project Close Date - July 29, 2022
Report to PARIS: Yes (Project 1801 22 04A)
Ivy Village Corp (Final Resolution Approved)
Ivy Village Corp is planning to construct a market-rate adult patio home development on 16 acres in the Village of Le Roy. The proposed $3.72 million project is for the construction of the initial 10 duplex residences (20 units total).
Project Application
Initial Resolution - Approved July 7, 2022
Public Hearing - July 26, 2022 - Notice - Minutes - Video
Final Resolution - Approved August 4, 2022
Agent Agreement
Project Close Date
Report to PARIS
Nexgistics
Nexgistics is planning to construct a 140,000 square-foot facility on Vision Parkway in the Town of Pembroke. The $17.6 million project includes a distribution center and national headquarters.
Project Application
Initial Resolution - Approved August 4, 2022
Public Hearing - August 22, 2022 - Notice - Minutes - Video
Final Resolution - Approved September 1, 2022
Agent Agreement
Project Close Date - March 10, 2023
Report to PARIS: YES (Project 1801 22 07A)
8250 Park Road LLC (Final Resolution Approved)
8250 Park Road LLC isplanningto purchase and renovate the former Quality Inn & Suites and Palm Island Indoor Water Park on Park Road in the Town of Batavia. The $12 million project will enable the company to upgrade the water park, hotel rooms, lobbies, event spaces, and on-site restaurant. The project pledges to create 38 full-time equivalanet positions.
Project Application
Initial Resolution - Approved October 6, 2022
Public Hearing - October 26, 2022 - Notice - Minutes - Video
Final Resolution - Approved November 1, 2022
Agent Agreement
Project Close Date
Report to PARIS
RPNY Solar 6 LLC (Final Resolution Approved)
RPNY Solar 6, LLC is proposing to construct a community solar farm project on Alexander Road in the Town of Batavia. The project will utilize 8,346 solar panels and 24 string inverters on approximately 17 of 29 acres on the property to convert the sun’s energy into 3 MW of AC power.
Project Application
Initial Resolution - Approved November 1, 2022
Public Hearing - November 21, 2022 - Notice - Minutes - Video
Final Resolution - Approved December 1, 2022
Agent Agreement
Project Close Date
Report to PARIS
RPNY Solar 7 LLC (Final Resolution Approved)
RPNY Solar 7, LLC is proposing to construct a community solar farm project on Alexander Road in the Town of Batavia. The project will utilize 6,214 solar panels and 20 string inverters on approximately 13 of 69 acres on the property to convert the sun’s energy into 2.5 MW of AC power.
Project Application
Initial Resolution - Approved November 1, 2022
Public Hearing - November 21, 2022 - Notice - Minutes - Video
Final Resolution - Approved December 1, 2022
Agent Agreement
Project Close Date
Report to PARIS
AES Rt 5 Storage LLC (Final Resolution Approved)
AES Rt 5 Storage,, LLC is proposing to construct a community solar farm project on West Main Road in the Town of Le Roy. The project will utilize ground-mounted solar panels to convert the sun’s energy into 5 MW of AC power.
Project Application
Initial Resolution - Approved November 1, 2022
Public Hearing - November 22, 2022 - Notice - Minutes - Video
Final Resolution - Approved December 1, 2022
Agent Agreement
Project Close Date
Report to PARIS
Hecate Energy Cider Solar LLC (Final Resolution Approved)
Hecate Energy Cider Solar LLC is proposing to construct a utility scale solar farm project at various properties in the towns of Elba and Oakfield. The project will be located on 2,455 acres and utilize solar panels mounted on tracking panel racks to convert the sun's energy into 500 MW of AC power, and will be interconnected with the electric grid.
Project Application
Initial Resolution - Approved November 1, 2022
Public Hearing (Elba) - November 28, 2022 - Notice - Minutes - Video
Public Hearing (Oakfield) - November 28, 2022 - Notice - Minutes - Video
Final Resolution - Approved December 1, 2022
Agent Agreement
Project Close Date
Report to PARIS
NY CDG Genesee 4 LLC (Final Resolution Approved)
NY CDG Genesee 4 LLC is proposing to construct a community solar farm on Shepard Road in the town of Pavilion. The solar project will be located on approximately 31 of 39 acres on the property to convert the sun's energy into 4.275 MW of AC power.
Project Application
Initial Resolution - Approved December 1, 2022
Public Hearing - January 4, 2023 - Notice - Minutes - Video
Final Resolution - Approved January 12, 2023
Agent Agreement
Project Close Date
Report to PARIS
2021 Projects
LandPro Equipment LLC - 1801 21 01A
LandPro Equipment LLC is proposing to acquire and develop a 14-acre parcel in the town of Batavia, including the construction of a 50,000 square-foot facility for a full-service John Deere Agriculture and Turf Dealership.
The company proposes to create 5 new jobs and retain 62 existing jobs as part of the $9.2 million project. The facility would service a customer base within a 50-mile radius of Batavia, NY and expand workforce training programs for the benefit of the company and Genesee County's workforce.
Project Application
Initial Resolution - Approved February 4, 2021
Public Hearing - February 24, 2021 - Notice - Minutes - Video
Final Resolution - Approved March 4, 2021
Agent Agreement
Project Close Date - June 25, 2021
Report to PARIS: Yes
Plug Power Inc. - 1801 21 04A
Plug Power Inc. is proposing a $232 million project at the Western New York Science & Technology Advanced Manufacturing Park in the town of Alabama. The operation will produce green hydrogen using an electrolysis process of water utilizing clean hydropower.
Project Application
Supplemental Application
Initial Resolution - Approved March 4, 2021
Public Hearing - March 22, 2021 - Notice - Minutes - Video
Public Hearing - June 3, 2021 - Notice - Minutes - Video
Final Resolution - Approved March 25, 2021
Supplemental Resolution - Approved June 3, 2021
Authorizing Resolution - Approved October 6, 2022
Agent Agreement
Project Close Date - November 8, 2021
Report to PARIS: Yes
Forefront Power LLC (Elba Solar) (Final Resolution Approved)
Forefront Power LLC is proposing a 5 MW community solar farm project in the Town of Elba (Elba School District) that will be interconnected with National Grid and provide power to subscribers.
Project Application
Initial Resolution - Approved March 4, 2021
Public Hearing - March 22, 2021 - Notice - Minutes - Video
Final Resolution - Approved May 6, 2021
Agent Agreement
Project Close Date
Report to PARIS: Project in Process
Solar Liberty 1 (Final Resolution Approved)
Solar Liberty is proposing a 4 MW community solar farm project in the Town of Pembroke (Akron School District) that will be interconnected with National Grid and provide power to subscribers.
Project Application
Initial Resolution - Approved March 4, 2021
Public Hearing - March 22, 2021 - Notice - Minutes - Video
Final Resolution - Approved March 25, 2021
Agent Agreement
Project Close Date
Report to PARIS: Project in Process
Solar Liberty 2 (Final Resolution Approved)
Solar Liberty is proposing a 5 MW community solar farm project in the Town of Pembroke (Akron School District) that will be interconnected with National Grid and provide power to subscribers.
Project Application
Initial Resolution - Approved March 4, 2021
Public Hearing - March 22, 2021 - Notice - Minutes - Video
Final Resolution - Approved March 25, 2021
Agent Agreement
Project Close Date
Report to PARIS: Project in Process
Excelsior Energy Center (Final Resolution Approved)
Excelsior Energy Center is proposing a 280 MW utility scale solar project in the Town of Byron (Byron-Bergen School District) that will be interconnected with the electric grid.
Project Application
Initial Resolution - Approved March 25, 2021
Public Hearing - April 19, 2021 - Notice - Minutes - Video
Final Resolution - Approved June 3, 2021
Agent Agreement
Project Close Date
Report to PARIS: Project in Process
Batavia Special Needs Apartments - 1801 21 09A
Batavia Special Needs Apartments, L.P. is proposing a $3.75 million expansion project in the City of Batavia. The applicant currently owns and operates a 42 unit building of special needs housing, and will construct an additional 20 units for a total of 62 units.
Project Application
Initial Resolution - Approved March 25, 2021
Public Hearing - April 14, 2021 - Notice - Minutes - Video
Final Resolution - Approved May 6, 2021
Agent Agreement
Project Close Date - September 15, 2021
Report to PARIS: Yes
NY CDG Genesee 1 LLC (Final Resolution Approved)
The company is proposing a 5 MW community solar farm project in the Town of Elba (Elba School District) that will be interconnected with National Grid and provide power to subscribers.
Project Application
Initial Resolution - Approved May 6, 2021
Public Hearing - May 17, 2021 - Notice - Minutes - Video
Final Resolution - Approved August 5, 2021
Agent Agreement
Project Close Date
Report to PARIS: Project in Process
Gateway GS, LLC - 1801 21 15A
Gateway GS LLC (Gallina Development) is proposing to build out a third building at the GCEDC's Gateway II Corporate Park in the town of Batavia. Facility will be 27,000 SF and will be completed in 2022 for a single logistics-distribution tenant.
Project Application
Initial Resolution - Approved July 1, 2021
Public Hearing - July 23, 2021 - Notice - Minutes - Video
Final Resolution - Approved August 5, 2021
Updated Final Resolution - Approved January 13, 2022
Authorizing Resolution - Approved March 3, 2022
Agent Agreement
Project Close Date - September 29, 2021
Report to PARIS: Yes
Trousdale Solar, LLC - 1801 21 12A
The company is proposing a 5 MW community solar farm project in the Town of Batavia (Batavia School District) that will be interconnected with National Grid and provide power to subscribers.
Project Application
Initial Resolution - Approved July 1, 2021
Public Hearing - July 23, 2021 - Notice - Minutes - Video
Final Resolution - Approved August 5, 2021
Agent Agreement
Project Close Date - April 7, 2022
Report to PARIS: Project in Process
Trousdale Solar II, LLC - 1801 21 13A
The company is proposing a 4 MW community solar farm project in the Town of Batavia (Batavia School District) that will be interconnected with National Grid and provide power to subscribers.
Project Application
Initial Resolution - Approved July 1, 2021
Public Hearing - July 23, 2021 - Notice - Minutes - Video
Final Resolution - Approved August 5, 2021
Agent Agreement
Project Close Date - April 7, 2022
Report to PARIS: Project in Process
Just Chez Realty (206 E. Main St.) - 1801 21 10A
Just Chez Realty, LLC, is proposing a $450,000 renovation project in the City of Batavia as part of Batavia's Downtown Revitalization Initiative. The project will create 2 market-rate apartments and follows the completion of first-floor improvements to the building.
Project Application
Final Resolution - Approved July 1, 2021
Agent Agreement
Project Close Date - February 28, 2022
Report to PARIS: Project in Process
Liberty Pumps - 1801 21 16A
Liberty Pumps is proposing to expand their operation in the Town of Bergen at Apple Tree Acres industrial park. The company is planning on constructing a warehouse and manufacturing space of 107,138 sf to support continuing growth of Liberty Pumps. The project is investing $13.7 million and is pledging to create 30 FTEs with an average salary of $52,000 annually plus benefits.
Project Application
Initial Resolution - Approved August 5, 2021
Public Hearing - August 26, 2021 - Notice - Minutes - Video
Final Resolution - Approved September 9, 2021
Agent Agreement
Project Close Date - November 21, 2021
Report to PARIS: Yes
Valiant Real Estate USA Inc - 1801 21 17A
Valiant Real Estate USA, Inc. is proposing to build a new 20,000 sq. ft. facility on the corner of Saile Drive and Call Parkway in the town of Batavia. The project is investing $4.5 million and is pledging to create 24 FTEs with an average salary range of $30,000-$75,000 annually plus benefits.
Project Application
Initial Resolution - Approved September 9, 2021
Public Hearing - October 5, 2021 - Notice - Minutes - Video
Final Resolution - Approved December 2, 2021
Agent Agreement
Project Close Date - December 21, 2021
Report to PARIS: Yes
J&R Fancher Property Holdings LLC (Brickhouse Commons LLC) - 1801 21 18A
J&R Fancher Property Holdings, LLC is proposing the to construct a 14,000 square foot 2-story mixed-used building on 2.6 buildable acres at Buffalo East Technology Park in Pembroke, NY.
The $1.7 million project includes the creation of 6 market rate 1-bedroom and 2-bedroom apartments on the second floor, and a 7,000 "vanilla" box interior space to attract commercial tenants.
Project Application
Initial Resolution - Approved September 9, 2021
Public Hearing - October 5, 2021 - Notice - Minutes - Video
Final Resolution - Approved October 7, 2021
Agent Agreement
Project Close Date - May 19, 2022
Report to PARIS: Project in Process
Mega Properties - 1801 21 19A
Mega Properties, Inc. is proposing to purchase a 147,000 square foot distribution facility on Federal Drive in the town of Batavia.
The project is investing $8.5 million and is pledging to create 11 FTEs with an average salary range of $30,000-$80,000 annually plus benefits.
Project Application
Initial Resolution - Approved December 2, 2021
Public Hearing - December 21, 2021 - Notice - Minutes - Video
Final Resolution - Approved January 13, 2022
Agent Agreement
Project Close Date - December 2, 2022
Report to PARIS: Project in Process
2020 Projects
Ellicott Station LLC - 801 21 07A
The Ellicott Station project is a proposed mixed-use brownfield redevelopment project including adaptive re-use and new construction of a blighted property in the city of Batavia. The $22.4 million total investment would complete the brownfield remediation of the 3.31-acre site, construct a new five-story modern workforce housing apartment building, and renovate an existing building for a restaurant/beer garden and brewery.
Project Application
Initial Resolution - Approved February 6, 2020
Public Hearing - March 3, 2020 - Notice - Minutes - Video
Final Resolution - Approved March 5, 2020
Authorizing Resolution - Approved July 1, 2021
Authorizing Resolution - Approved October 28, 2021
Agent Agreement
Project Close Date - July 21, 2021
Report to PARIS: Yes